Thursday, 24 November 2016

Fourth Post - Project timelines



Fourth Post - How will you do it?

Project timelines

Tasks
Timeline
Feedback required?

Give client access to Blog
Immediately
Yes, if any problems with accessing site

Present design and colours including materials board
1 week
Yes
Agree on project details and budget constraints
1 week
Yes
Purchase of materials (paint/lighting)
2 days

Electrician to fit new lighting
1 to 2 days


Painting of area including preparation
4 days

Clean, final check/inspection
Morning


Final inspection by client
TBA
Yes

Feedback from client

Yes

Third Post - Resources & Equipment

Equipment & Resources :

Computer with internet access
- To enable research into 80's theme and to produce Blog for client

Paint (exact amount to be confirmed)
- Including undercoat, safety equipment and labour to undertake the task

Lighting
- Purchase lighting (including bulbs etc), installation to be carried out by licensed electrician

Budget
- Confirm any budget restrictions with the client and give estimate with any necessary payment instalment dates